Freightline Maastricht-Lanaken
|
Viaduct Fort Willemweg |
||||
|
||||
|
|
|
|||
![]() |
|
|||
![]() |
In the mean time one is preparing the deck. The rivets are being removed with torches. |
|||
![]() |
From under the steel plates surprisingly wooden sleepers surface. Around this hour ( 21:30) it starts to rain a bit.... |
|||
![]() |
It has become dark as the first bridgepart is lifted. |
|||
![]() |
At 23:50 the bridge segment on the pavement for further handling. to remove the whole bridge and preparing it for transport takes to the little hoursof 14 June. |
|||
![]() |
The viaduct across the Fort Willemweg one week later. |
|||
![]() |
Vista through the Fort Willemweg in the direction of the sluice 19. |
|||
![]() |
View over the trace from the Fort Willemweg in direction of the city of Maastricht. Old rails and switches have been removed. |
|||
![]() |
View over the trace from the Fort Willemweg in direction Lanaken. The tracks from the former railway yard have been removed already. On the left once was the Boschpoort stationhouse. |
|||
|
Update 31 Aug 2008 |
||||
![]() |
|
|||
![]() |
|
|||
![]() |
|
|||
![]() |
|
|||
![]() |
|
|||
![]() |
|
|||
![]() |
|
|||
![]() |
|
|||
|
|
|
|||
![]() |
The approach to the former Boschpoort station has been cleared on behalf of the works. |
|||
![]() |
|
|||
![]() |
|
|||
![]() |
|
|||
|
Underpass Sillebergweg |
||||
|
The brickwork of this tunnel will be repaired and freshly pointed. |
||||
![]() |
|
|||
![]() |
|
|||
|
Update 16 Nov 2008 |
||||
![]() |
|
|||
![]() |
|
|||
|
Recommended website