For years there have been plans
for electrification of this part of the line between Montzen-Gare
and Reinartzkehl. To realize this effort first the bridges and
viaducts had to be prepared to carry the pylons and at Nouvelaer a
complete new viaduct had to be built. Now all conditions are met, at
the beginning of July 2008 the
electrification will be a fact. From then on it will be possible to
transport the
shuttles from Antwerp to Cologne directly without the cumbersome
shunter movements at Montzen-Gare and
Aachen-West. It will deliver enormous timesaving and both shunting
yards will loose their importance and size!
|
|
| |
|
|
|
|
| |
 |
An other obstacle
is the old tunnel at Botzelaer. It is not possible to dig it deeper
because of the way it is built. The tunnel originates from 1872 and
originally belonged to the Line 39 Aachen-Plombières.
( July 28,
2005 )
|
|
| |
|
|
|
|
| |
 |
A close-up of the tunnelporch in April
2008. Until here the german net is led through the tunnel. ( April
27, 2008 )
|
|
| |
|
|
|
|
| |
 |
Heavy weights keep the tension on
thewire .
A transformer house is under construction. ( April
27, 2008 )
|
|
| |
|
|
|
|
| |
 |
The new overhead wires will take away our free view on the
tunnel in future. ( April
27, 2008 )
|
|
| |
|
|
|
|
| |
 |
In the past weekends the traffic
was diverted via the Buschtunnel, so at this place one could work
undisturbed. On monday afternoons the traffic through the
tunnel would be normalized. ( April
27, 2008 )
|
|
| |
|
|
|
|
| |
 |
The solution
for the suspension of the wires inside the tunnel was found by using
this spring mounted
rail-construction at the ceiling of the tunnel. ( April
27, 2008 )v
|
|
| |
|
|
|
|
| |
 |
View inside the tunnel where a crew is still working.
Until now it was presumed that it would only be possible to hang
only one wire above the middle track, and that the tunnel would
still remain a bottleneck. ( April 27, 2008 )
|
|
| |
|
Update June 2008 |
|
|
| |
 |
The substation is growing slow,
but steady.
Wikipedia. ( 24
june 2008 )
|
|
| |
|
Update 10 Aug 2008 |
|
|
| |
 |
The substation is growing slow,
but steady. (
10 Aug 2008 )
|
|
| |
|
|
|
|
| |
 |
The new pylons
already have crossbars. (
10 Aug 2008 )
|
|
| |
|
Update 30 Nov 2008 |
|
|
| |
 |
The substation
is almost complete, at this moment the doors still had to be placed. (
12 Okt 2008 )
|
|
| |
|
|
|
|
| |
 |
|
| |
|
|
| |
 |
At Botzelaer is the seperation between the belgian and german
traffic oversight. ( April
27, 2008 )
|
|
| |
|
|
|
|
| |
 |
Momentarily at
Gemmenich-Oost holes are being digged
for the foundations of the pylons. Here a mould is placed, which
will be casted in concrete. After the concrete is hardened, the
mould is taken out, leaving a hole for placing the pylon. ( April
27, 2008 )
|
|
| |
|
|
|
|
| |
 |
Further on in the direction of Nouvelaer only holes. ( April
27, 2008 )
|
|
| |
|
Update 27 July 2008 |
|
|
| |
 |
View in direction Botzelaer tunnel,
on the right pylons have been placed recently.
( 27 July 2008 )
|
|
| |
|
|
|
|
| |
 |
The worktrain of the Duchene Company from
Modave (Near Huy) placing pylons.
( 27 July 2008 )
|
|
| |
|
|
|
|
| |
 |
The train is pulled by the
NMBS 7351 with
the nickname "ECHO", stationed in Visé.
( 27 July 2008 )
|
|
| |
|
|
|
|
| |
 |
The
crane in action with a pylon.
( 27 July 2008 )
|
|
| |
|
|
|
|
| |
 |
In the mean time traffic on the
other track as
usual. Here a pair of NMBS serie 55ers
with a long freight train heading for Montzen.
( 27 July 2008 )
|
|
| |
|
Train composition : |
|
|
| |
 |
Water Tankcar : 910 0
113-4 Maintainance car 1 : (-) Concrete mixer car : (-) Gravel
car
1 : 930 0 165-3
Gravel car 2
: 930 0 163-8 Gravel car 3
: 930 0 166-1
|
|
| |
|
Maintainance car
2 : 910 0 103-5
Rebar car 1 : (-)
Crane car
: 930 0 161-4 (Crane : Palfinger PKR 480)
Rebar car 2 : (-)
( 27 July 2008 )
|
| |
|
|
|
|
| |
 |
 |
| |
|
|
|
|
| |
 |
The old viaduct at Nouvelaer is not high enough to have room for
the overhead wires. ( Aug 25, 2007 )
|
|
| |
|
|
|
|
| |
 |
Therefor a new viaduct is being built since autumn 2007. ( April
27, 2008 )
|
|
| |
|
|
|
|
| |
 |
Detail of the new viaduct. ( April 27, 2008 )
|
|
| |
|
Update 27 July 2008 |
|
|
| |
 |
The two viaducts next to each other. ( 27 July 2008 )
|
|
| |
|
|
|
|
| |
 |
One side of the new viaduct was coated with natural stone.
The other side has to be done yet. ( 27 July 2008 )
|
| |
|
Update 10 Aug 2008 |
|
|
|
| |
 |
View in direction Botzelaer. ( 10 Aug 2008 )
|
|
| |
|
|
|
|
| |
 |
From the viaduct in direction Aix. The pylons here still have no
crossbars. The work is now mainly done during night time ! ( 10 Aug 2008 )
|
| |
|
Update 30 Nov 2008 |
|
|
| |
 |
The new viaduct is ready, the old one has been removed already ! ( 12 Okt 2008 )
|
|
| |
|
|
|
|
| |
 |
This is the new view from the viaduct in direction
Botzelaar ! The overhead wiring now completed from Montzen to
Reinartzkehl ! ( 12 Okt 2008 )
|
|
| |
|
|
|
|
| |
|